Fast-tracked fitout of the Delta Check-In area at Terminal 1 within just 16 days.
The scope of works included demolition, installation of new check-in counters, partitions, flooring, and joinery. This project was completed in a live operational environment, requiring precise coordination to ensure zero disruption to daily airport operations.
Strategic staging, after-hours work, and tight coordination across joinery, electrical, data, and communications services were key to achieving the accelerated schedule. All systems were delivered in full compliance with operational and regulatory standards, ensuring seamless integration and uninterrupted movement for end users.
Project details
- Region
- Sydney, NSW
- Sector
- Aviation
- Status
- Complete
Completed in 2018